Siddhirganj 2X120 MW Peaking Power Plant
Client
Asian Development Bank, Electricity Generation Company of Bangladesh (EGCB)
Sector
Energy and Power
Country
Bangladesh
Timeline
2006-2011
Project Description
Assist Electricity Generation Company of Bangladesh Ltd. (EGCB) in the implementation of the Siddhirganj 2 X 120 MW Peaking Power Plant by a 2 X 120 MW Gas Turbine, 3 X 10 MW steam plants, and 50 MW steam plant for Peaking Power Station at the Siddhirganj site.
Environmental impact assessment for the project.
Providing assistance on evaluation of bids, examination and checking contract documents & contractor’s report.
Supervision of demolition works as per standard safety & waste disposal regulations and monitor compliance of Environmental Regulations.
Checking, recommending and approving the drawings, specifications, and detailed work schedule submitted by the Turnkey Contractor.
Verifying contractor’s invoices, reviewing schedule of contractor’s work and contractor’s documents (engineering / procurement).
Supervised construction, testing, commissioning, and recommended provisional taking over certificate.
Witnessing factory tests, investigating and providing approval of the method for trial operation, test, commissioning procedures and acceptance tests.
Organizing and supervising local training provided by the Turnkey Contractor.
Checking the list of materials of the Stores handed over to EGCB vis-à-vis Contract Document